We would love to have help on this project or just company at our camp site. Below is a projected work schedule to get the house enclosed. You can see that there are many jobs to be completed between now and the date I would like the walls to begin going up. Much of this is in the hands of professionals and inspectors, so it is difficult to know when these things can be accomplished.
If you can come out and help or visit, this should give some idea when we expect to be there and what will need to be done. Chances are good that the 6/19 walls date will be pushed back. I will update the chart as work progresses.
If you think you will come down, leave a comment or ping me privately to let me know when and I will be sure to keep you in the loop.
| Job | Owner | Start Date | Help Needed |
| Plumbing Layout | Jeff | June 4 | |
| Dig plumbing trenches | Josh | June 5 | |
| Underground plumbing & inspection | Jeff | ||
| Prep for floor pour & inspection | Barry | ||
| Install hydronic tubes | Josh | 0-1 | |
| Pour floor | Barry | ||
| Pressure test hydronic | Josh | ||
| Plumbing rough in & inspection | Jeff | ||
| Foundation inspection | Barry | ||
| Begin putting up walls | Josh | June 19 | 2 |
| Raise center ring, 4 rafters | Josh | June 26 | 2 |
| Remaining rafters | Josh | June 27 | 2 |
| Rough in ceiling electrical | Josh | June 29 | 1 (Carol) |
| Framing inspection | Steve | ||
| Build addition entryway | Josh | June 30 | 1 |
| Install pine T&G ceiling | Josh | July 3 | 2 |
| Spray Insulation | Bob | ||
| Install roof | Josh | July 10 | 2 |
I’ll be renting a porta-potty beginning the day we start putting up walls. We expect to be camped out there for several solid weeks so we will need it.
Things are really moving along! Looks like you’re getting into the thick of it now…good luck with the building process! Love, Diane
LikeLike