Schedule

We would love to have help on this project or just company at our camp site.  Below is a projected work schedule to get the house enclosed.  You can see that there are many jobs to be completed between now and the date I would like the walls to begin going up.  Much of this is in the hands of professionals and inspectors, so it is difficult to know when these things can be accomplished.

If you can come out and help or visit, this should give some idea when we expect to be there and what will need to be done.  Chances are good that the 6/19 walls date will be pushed back.  I will update the chart as work progresses.

If you think you will come down, leave a comment or ping me privately to let me know when and I will be sure to keep you in the loop.

Job Owner Start Date Help Needed
Plumbing Layout Jeff June 4
Dig plumbing trenches Josh June 5
Underground plumbing & inspection Jeff
Prep for floor pour & inspection Barry
Install hydronic tubes Josh 0-1
Pour floor Barry
Pressure test hydronic Josh
Plumbing rough in & inspection Jeff
Foundation inspection Barry
Begin putting up walls Josh June 19 2
Raise center ring, 4 rafters Josh June 26 2
Remaining rafters Josh June 27 2
Rough in ceiling electrical Josh June 29 1 (Carol)
Framing inspection Steve
Build addition entryway Josh June 30 1
Install pine T&G ceiling Josh July 3 2
Spray Insulation Bob
Install roof Josh July 10 2

I’ll be renting a porta-potty beginning the day we start putting up walls.  We expect to be camped out there for several solid weeks so we will need it.

 